Phase I-N
Phase I-N

Phase I-N

Schedule:
Mid-February, through Mid-June, 2023

Description:
Construction of the new, offline, portions of Rabbit Road and SE Connector between Oshara Boulevard and Rabbit Road

Route Impacts:

  • No closures are anticipated.

  • Construction related traffic will be using area roads to access various portions of the site.

Overlap:
Phase I-S

Phase I-S

Phase I-S

Schedule:
Mid-February, through late January, 2024

Description:
Construction of the new, offline, portions of Rabbit Road and SE Connector south of Oshara Boulevard and Avenida del Sur east of the Richards Avenue intersection.

Route Impacts:

  • No closures are anticipated.

  • Construction related traffic will be using area roads to access various portions of the site.

Overlap:
All Phases

Phase IA

Phase IA

Schedule:
Late June, through mid-August, 2023

Description:
Reconstruction of Dinosaur Trail/Rabbit Road and Richards Avenue intersection.

Overlap:
Phase I-S

Route Impacts:

  • Richards Avenue Closed between Beckner Road and Dinosaur Trail. The existing Dinosaur Trail and Richards Avenue intersection provided access to Richards Avenue south of Dinosaur Trail.

  • Construction related traffic will be using area roads to access various portions of the site.

Phase II-A

Phase II-A

Schedule:
Mid-August, through late September, 2023

Description:
Construction of connection between the existing and proposed Rabbit Road segments.

Route Impacts:

  • Closure of Rabbit Road east of the western project limit.

  • Construction related traffic will be using area roads to access various portions of the site.

Overlap:
Phases I-S and IV

Phase II-B

Phase II-B

Schedule:
Late September, through mid-December, 2023

Description:
Construction of the Oshara Boulevard and SE Connectors intersection.

Route Impacts:

  • Closure of existing Rabbit Road to Oshara Boulevard connection.

  • Construction related traffic will be using area roads to access various portions of the site.

Overlap:
Phases I-S and IV

Phase III

Phase III

Schedule:
Mid-December, through late January, 2024

Description:
Construction of connection between the existing and proposed Dinosaur Trail segments.

Overlap:
Phase I-S

Route Impacts:

  • Closure of Dinosaur Trail west of Richards Avenue.

  • Construction related traffic will be using area roads to access various portions of the site.

Phase IV

Phase IV

Schedule:
Mid-August, through Mid-October, 2023

Description:
Reconstruction of Avenida del Sur and Richards Avenue intersection.

Overlap:
Phase I-S, II-A, -B

Route Impacts:

  • Closure of the Avenida del Sur and Richards Avenue Intersection.

  • Construction related traffic will be using area roads to access various portions of the site.