Phase I-N
Phase I-N
Schedule:
Mid-February, through Mid-June, 2023
Description:
Construction of the new, offline, portions of Rabbit Road and SE Connector between Oshara Boulevard and Rabbit Road
Route Impacts:
-
No closures are anticipated.
-
Construction related traffic will be using area roads to access various portions of the site.
Overlap:
Phase I-S
Phase I-S
Phase I-S
Schedule:
Mid-February, through late January, 2024
Description:
Construction of the new, offline, portions of Rabbit Road and SE Connector south of Oshara Boulevard and Avenida del Sur east of the Richards Avenue intersection.
Route Impacts:
-
No closures are anticipated.
-
Construction related traffic will be using area roads to access various portions of the site.
Overlap:
All Phases
Phase IV
Phase IV
Schedule:
Mid-May, through mid-July, 2023
Description:
Reconstruction of Avenida del Sur and Richards Avenue intersection.
Overlap:
Phase I-N and I-S,
Route Impacts:
-
Closure of the Avenida del Sur and Richards Avenue Intersection.
-
Construction related traffic will be using area roads to access various portions of the site.
Phase I-A
Phase I-A
Schedule:
Mid-July, through mid-September, 2023
Description:
Reconstruction of Dinosaur Trail/Rabbit Road and Richards Avenue intersection.
Overlap:
Phases I-S
Route Impacts:
-
Richards Avenue Closed between Beckner Road and Dinosaur Trail. The existing Dinosaur Trail and Richards Avenue intersection provided access to Richards Avenue south of Dinosaur Trail.
-
Construction related traffic will be using area roads to access various portions of the site.
Phase II-A
Phase II-A
Schedule:
Mid-September, through early October, 2023
Description:
Construction of the Oshara Boulevard and SE Connectors intersection.
Route Impacts:
-
Closure of existing Rabbit Road to Oshara Boulevard connection.
-
Construction related traffic will be using area roads to access various portions of the site.
Overlap:
Phases I-S
Phase II-B
Phase II-B
Schedule:
Early October, through mid-December, 2023
Description:
Construction of the Oshara Boulevard and SE Connectors intersection.
Overlap:
Phase I-S
Route Impacts:
-
Closure of existing Rabbit Road to Oshara Boulevard connection.
-
Construction related traffic will be using area roads to access various portions of the site.
Phase III
Phase III
Route Impacts:
-
Closure of Dinosaur Trail west of Richards Avenue.
-
Construction related traffic will be using area roads to access various portions of the site.
Schedule:
Mid-December, through late January, 2024
Description:
Construction of connection between the existing and proposed Dinosaur Trail segments.
Overlap:
Phase I-S